|
         
|
Overview Description of the CSO Control Program
The NPDES Program Requirements
In the late 1980s the predecessor agency of the Michigan Department
of Environmental Quality (MDEQ) established a definition of adequate
treatment of combined sewer overflows (CSOs) as part of its National
Pollutant Discharge Elimination System (NPDES) permitting program.
Under this definition, CSOs must be eliminated through sewer separation
or through the construction of basins capable of detaining the 10-year/1-hour
storm for 30 minutes, and completely capturing the 1-year/1-hour
storm. This generally requires a basin volume equal to 0.35 inches
of rain multiplied over the drainage area served by the basin. Twenty-seven
NPDES permits for CSO discharges were issued by the MDEQ to Wayne
County, Oakland County Drain Commissioner and to the combined sewered
communities. The level of control required to meet the definition
of adequate treatment was a major issue since the estimated costs
for achieving compliance with the permits ranged from approximately
$1 billion to $3 billion, depending on the level of treatment chosen.
Believing that a smaller level of control would meet water quality
objectives, the CSO communities contested the proposed NPDES permits.
Negotiations were conducted with the assistance of a U.S. District
Court appointed monitor in an attempt to identify a less costly
first round CSO control program and to avoid lengthy litigation
over the permit requirements. The negotiations led to a settlement
document (the Bulkley Agreement) that was incorporated into formal
modifications of the disputed NPDES permits in October 1992. The
revised permits required each permittee, at selected CSOs, to construct
and evaluate varying sizes of CSO basins, known as demonstration
basins. A two-year period was established in the permit to evaluate
the performance of what was called the Phase I CSO control basins.
Evaluation findings would then establish the level of control needed
for the remaining CSOs in the watershed. Such controls would be
implemented in Phase II of the program. Phases I and II controls
were to achieve the elimination of raw sewage and the protection
of public health. Phase III of the control program would require
the installation of additional controls, if needed, in order to
achieve water quality standards in the Rouge River.
The Rouge River National Wet Weather Demonstration Project
Recognizing the major costs involved in controlling CSOs and that
other sources of pollution impacted water quality, Congress appropriated
money through the United States Environmental Protection Agency
(USEPA) to Wayne County, Michigan for the creation of the Rouge
River National Wet Weather Demonstration Project (Rouge Project)
in 1992. The Rouge Project was thus born out of a desire and critical
need to manage the multiple sources of pollution in this urban watershed
in a prioritized, comprehensive manner. The Rouge Project is a comprehensive
program to manage wet weather pollution to restore the water quality
of the Rouge River, a tributary of the Detroit River in Southeast
Michigan. The Rouge River watershed is largely urbanized, spans
approximately 438 square miles, and is home to over 1.5 million
people in 48 communities and 3 counties. Sources of pollution to
the river include industrial and municipal point sources, CSOs,
storm water runoff, discharges from illicit connections, discharges
from failed on-site septic systems, and resuspension of contaminated
sediment. An MDEQ aggressive NPDES permitting process is successfully
addressing the point sources and combined sewer overflows. However,
water quality is adversely impacted from nonpoint pollution sources
and from problems such as erosion and loss of habitat associated
with variable flow regimes. For
additional information on the overall Rouge Project, click here.
The Rouge Project was designed and implemented to identify the
most efficient and cost effective controls of wet weather pollution,
while assuring maximum use of the resource-the Rouge River. The
early focus of the Rouge Project was on the control of the 168 CSOs
in the older urban core portion of the downstream areas of the Rouge
watershed. The eastern side of the watershed including the downstream
areas consists of much of the older industrial areas in southeast
Michigan. The western side of the watershed consists of newer suburban
development and areas under heavy development pressure. Almost all
sanitary and combined sewers in the watershed are connected to the
Detroit sewerage system for treatment at the Detroit Wastewater
Treatment Plant that discharges outside of the watershed into the
Detroit River. Combined sewers serve twenty percent of the watershed.
Separate sanitary and storm sewers serve most of the remaining areas
of the watershed with the exception of isolated pockets and rural
areas in the headwaters that still have on-site septic systems.
The CSO objectives of the Rouge Project include the goal of adding
to the knowledge base for CSO characteristics and control options.
Specifically, the Rouge Project has aimed to provide insight on
design of CSO control facilities so that they can achieve better
pollutant removal and a greater beneficial impact on the receiving
stream. Secondly, the experience gleaned from the operation of the
Rouge CSO control facilities has provided an opportunity for information
sharing of operations and maintenance issues that may assist in
future designs or in operations of other facilities around the country.
Third, the evaluation of the completed CSO control facilities has
assessed the necessary level of CSO control needed to meet water
quality standards. A fundamental tenet of the Rouge Project is the
information gained would be a demonstration for others in the country
to use as they proceed with their CSO control program.
CSO controls are being implemented in three phases:
- Phase I elimination of raw sewage and the protection of public
health for approximately 40 percent of the combined sewer area
- Phase II elimination of raw sewage and the protection of public
health for the remaining combined sewer area
- Phase III meet water quality standards in the Rouge River
A two-year period was established in the permits to evaluate the
performance of the CSO control basins implemented under Phase I
of the program. Evaluation findings would then establish the level
of control needed for the remaining CSOs in the watershed. Such
controls would be implemented in Phase II of the program. As noted,
Phase I and Phase II controls were to achieve the elimination of
raw sewage and the protection of public health. Phase III of the
control program would require the installation of additional controls,
if needed, in order to meet water quality standards in the Rouge
River.
Sewer Separation
Under Phase I, six communities separated their sewers thereby eliminating
19 CSO outfalls. Table 1 summarizes the major elements of those
projects.
Table 1
Sewer Separation Projects
| Location |
Area |
Separated Approximate Length of New
Sanitary Sewers and Storm Sewers |
| Bloomfield Hills |
86 acres |
3 miles |
| Garden City |
1180 acres |
23 miles |
| Livonia |
103 acres |
2 miles |
| Plymouth Township |
138 acres |
1 mile |
| Wayne |
288 acres |
4 miles |
| Westland |
409 acres |
8 miles |
CSO Retention Treatment Basins
Under Phase I, eight communities constructed 10 retention/treatment
basins for storing and treating combined sewer overflows, controlling
or partially controlling 64 of the outfalls. Click on the following
to see the locations of the combined and separated
areas and the location of the retention
treatment basins. Each of these basins is sized for different
design storms and several employ innovative technology. With one
exception (River Rouge), the CSO retention treatment basins constructed
under Phase I of the Rouge Project were intended to meet demonstration
criteria rather than presumptive criteria A range in sizing criteria
was established as part of the permit negotiations. The design criteria
for the basins vary according to the facilities' design storm and
detention times. Basin volumes range from 0.06 inches to 0.40 inches
of rain multiplied over the drainage area, with a majority of the
CSO facilities having volumes between 0.13 inches to 0.17 inches.
Facilities also incorporate a variety of additional features or
variations in compartment sizing and sequencing in an effort to
improve their effectiveness.
Specific design criteria for each basin are included in Table 2.
This table also includes the costs of the basins in year 2003 dollars.
Both total costs and unit costs are provided. The unit costs ranged
from a low of $2.51 to a high of $8.53 per gallon of storage. These
costs are for the basins only and do not include any consolidation
sewers to collect flows from several outfalls. Funding for the design
costs were provided at 90% by the federal dollar, with 10% from
local sources. Regular construction was covered at 55% federal and
45% local. Innovative feature such as the swirl concentrator was
funded at 95% federal and 5% local.
Table 2
Rouge Project Phase I CSO Retention Treatment Basin
Design Information
|
Table 2 Rouge Project Phase I CSO Retention Treatment
Basin Design Information
|
|
Basin
|
Combined & Storm Drainage Area
|
Separate Sanitary Drainage Area
|
Basin Volume
|
In-System Storage Volume
|
Design Storm
|
Detention Time
|
Construction Costs***
|
|
(Acres)
|
(Acres)
|
(MG)
|
(Inches)*
|
(MG)
|
|
(Minutes)
|
$M
|
$/Gal.
|
|
Wayne County
|
Inkster
|
838
|
548
|
3.1
|
0.14
|
1.0
|
1yr, 1hr (1.0 in)
|
20
|
16.7
|
6.71
|
|
Redford
|
669
|
1,622
|
1.9
|
0.10
|
0.24
|
1yr, 1hr (1.0 in)
|
20
|
13.0
|
8.53
|
|
Dearborn Heights
|
360
|
0
|
2.7
|
0.28
|
0.7
|
10yr, 1hr (1.75 in)
|
30
|
17.7
|
8.08
|
|
Oakland County
|
Acacia Park
|
816
|
0
|
4.0
|
0.18
|
0.5
|
1yr, 1hr (1.0 in)
|
30
|
10.7
|
3.33
|
|
Birmingham
|
1,185
|
0
|
5.5
|
0.17
|
4.1
|
1yr, 1hr (1.0 in)
|
30
|
12.6
|
2.86
|
|
Bloomfield Village
|
1735
|
590
|
10.0
|
0.21
|
0.2
|
1yr, 1hr (1.0 in)
|
30
|
20.1
|
2.51
|
|
Detroit
|
Seven Mile
|
463
|
0
|
2.2
|
0.17
|
2.5
|
1yr, 1hr (1.0 in)
|
30
|
15.0
|
8.48
|
|
Puritan-Fenkell
|
649
|
0
|
2.8
|
0.16
|
6.2
|
1yr, 1hr (1.0 in)
|
20
|
18.2
|
8.01
|
|
Hubbell-Southfield
|
14,400
|
0
|
22.0
|
0.06
|
4.4
|
Built within site constraints
|
54.9
|
3.11
|
|
River Rouge**
|
929
|
0
|
5.2
|
0.21
|
1.9
|
1yr, 1hr (1.0 in)
|
Capture
|
25.9
|
6.20
|
|
10yr, 1hr (1.75 in)
|
30
|
* Inches of runoff over
combined and storm drainage area
** Designed for presumptive criteria – meets both
criteria given for design storm and detention time
*** Construction costs do not include costs for any sewers used
to consolidate outfalls. Escalation to 2003 dollars based
on Engineering News Record Index.
MG – million gallons
Nine of the retention/treatment basins have been fully operational
since 1998 or earlier and have detailed information evaluating their
overall performance. The tenth CSO basin, River Rouge, became operational
in the spring of 2002; evaluation of this facility is ongoing. A
Phase I tunnel project designed to serve some of the CSO areas ran
into constructability problems and is now being redesigned as individual
CSO control facilities at each outfall rather than a tunnel.
What follows is a brief summary of how the retention/treatment
basins operate. The basins are designed to capture the first flush
flows and to then route flows to a second flow-through compartment
after the first compartment is full. This prevents the discharge
of any pollutant loads that may be captured with the first flush,
which has been found to have higher concentrations of pollutants.
The basins are dewatered after a storm water event when capacity
is available in the receiving interceptor for conveyance to the
Detroit wastewater treatment plant. The facilities all included
influent or effluent screens, skimming baffles, storage and settling
basins that can capture small events or work in a flow-through mode
for large events. All facilities are designed to meet NPDES effluent
limits for fecal coliform of 400 cts / 100 ml and an effluent goal
for total residual chlorine (TRC) of 1 mg/L. A basin only discharges
treated effluent to the Rouge River during large rainfall events
when the basin is full and the interceptor sewer is unable to accept
any more water for conveyance to the treatment plant. Note that
the treated overflows occur when the assimilative capacity of the
river is the greatest due to the higher river flows. The CSO basins
are dewatered when the interceptor sewer is able to accept the flows.
Most of the CSO basins use tipping buckets to remove settled debris
after an event. The basins have to be good neighbors to surrounding
land uses, which include nature centers, a golf course, and recreational
facilities.
CSO Basin Evaluations
A detailed evaluation study of the CSO control basins utilizing
approximately two years of sampling at each basin was undertaken
to examine the performance of the facilities and the water quality
impacts of their discharges. The results of the evaluation study,
coupled with efforts to control storm water and other pollution
sources in the watershed, is providing the basis for the Phase II
and Phase III CSO control program on the remaining CSO sources in
the watershed. The information gained from the evaluation of design
storms and control technologies is useful nationwide for determining
cost effective CSO controls to meet water quality standards.
There are four key questions being asked by MDEQ of the evaluation
of the CSO control basins: (1) Is the discharge from a CSO control
facility clean enough to meet water quality standards? (2) What
in-stream impacts should be measured? (3) How can the in-stream
impacts of CSOs be evaluated when there are other sources of wet
weather in the watershed? (4) When is there enough data to make
decisions?
The MDEQ established a process for
assessing compliance with the NPDES permits and the phased CSO
control requirements in order to answer the above questions. The
process fully involved the Rouge Project and the CSO communities.
The MDEQ established three CSO Retention/Treatment Basin (RTB) Committees
to analyze discharge data from groups of RTBs. The RTB Committee
reviews discharge data in relation to the Phase
II Criteria for Success in CSO Treatment established by MDEQ
with input from the Rouge Project and the CSO Communities. The Rouge
Stream Data Committee evaluates receiving stream data for impacts
from the individual RTBs. The Committee then determines whether
the receiving water downstream from each individual RTB is achieving
the Phase II criteria for success and, if not, to what extent the
RTB discharge is contributing to the water quality problem. Finally,
the CSO Workgroup compiles the information on success of the individual
RTBs in meeting the Phase II and Phase III criteria for success
and proposes what level of treatment should be considered adequate.
The Workgroup is composed of MDEQ staff and representatives of the
RTB communities.
In February 2001, the Rouge Stream Data Committee issued its Interim
Report in which they analyzed the data collected to assess the effectiveness
of the CSO demonstration basins and whether the receiving water
downstream from each basin is achieving Phase III criteria for success
and, if not, to what extent are the basins contributing to the remaining
water quality problems. The MDEQ Phase III criteria for success
state that achievement of state water quality standards (WQS) at
times of discharge will be measured by the following criteria:
- the dissolved oxygen (DO) standard;
- the physical characteristics standard;
- the total residual chlorine (TRC) standard; and
- the health of the biological community (as a surrogate for toxic
materials and other pollutants).
Additional details of the in-stream evaluation process can be found
in the paper titled "Evaluation
of In-Stream Impacts of CSO Control Facilities." For other
reports on the CSO control program, please see Products
and Data, Combined Sewer Overflows.
It is very important to note that MDEQ has concluded that nine
of the CSO retention treatment facilities are currently meeting
the Phase II criteria of the elimination of raw sewage and the protection
of public health. A June 9, 2000 Letter
of Approval for Phase II Review focused on the following retention
treatment basins: Acacia Park CSO Retention Treatment Basin, Birmingham
CSO Retention Treatment Basin, and Bloomfield Village CSO Retention
Treatment Basin. The August 7, 2000
Letter of Approval for Phase II Review focused on the following
retention treatment basins: Inkster CSO Retention Treatment Basin,
Dearborn Heights CSO Retention Treatment Basin, Redford Township
CSO Retention Treatment Basin. A February 14, 2002 Letter of Approval
for Phase II Review focused on the following retention treatment
basins for the City of Detroit: Hubbell-Southfield CSO Retention
Treatment Basin, Puritan-Fenkell CSO Retention Treatment Basin,
and Seven Mile CSO Retention Treatment Basin. In addition, the three
Oakland County CSO basins (Acacia Park, Birmingham, and Bloomfield)
are achieving the Phase III goal of meeting water quality standards
at times of discharge, except for meeting the yet-to-be-evaluated
total residual chlorine standard. This Phase III certification is
expected on the other six basins very soon. The tenth CSO basin,
River Rouge, became operational in March 2002. Its performance will
be evaluated over the next two years.
Evaluation of the Performance of the CSO Basins: What the Rouge
Project Has Learned
As stated earlier, each of the retention/treatment basins is sized
for different design storms and several employ innovative technology.
The CSO basins also incorporate a variety of additional features
or variations in compartment sizing and flow sequencing in an effort
to improve their effectiveness. As stated earlier, a two-year period
was established in the NPDES permits to evaluate the performance
of the CSO control basins implemented under Phase I of the program.
Evaluation findings would then establish the level of control needed
for the remaining CSOs in the watershed. Such controls would be
implemented in Phase II of the program. Phase I and Phase II controls
were to achieve the elimination of raw sewage and the protection
of public health. Phase III of the control program would require
the installation of additional controls, if needed, in order to
meet water quality standards in the Rouge River. Working with the
local communities, the MDEQ established rigorous "Criteria
for Success in CSO Treatment" to evaluate whether the CSO
basins met the goals established for each phase of the program.
The process by which these Criteria were established and the specific
details of the criteria are explained in documents contained on
the Rouge Project web site and therefore will not be discussed here.
A detailed evaluation of the approximately two years of sampling
at each of the CSO retention treatment basin for which data were
available (nine basins) was undertaken to examine the performance
of the facilities and the water quality impacts of their discharges.
Details of the protocols used and the full results of all studies
are available on the Rouge River web site. (See "Technical
Papers and Professional Presentations on CSO Control Program").
The results of the evaluation study, coupled with efforts to control
storm water and other pollution sources in the watershed, are providing
the basis for the Phase II and Phase III CSO control program on
the remaining CSO sources in the watershed. The information gained
from the evaluation of design storms and control technologies is
also being used to demonstrate cost effective CSO controls. This
information is needed for nationwide use in implementing the national
CSO Control Policy embodied in the Clean Water Act.
In order to make the wealth of data gathered during the two-year
evaluation program at each retention/treatment basin more available,
the Rouge Project summarized the more important findings in a report
titled: "CSO
Basins: Getting the Most Performance for Your Pollution Control
Dollar" (hereinafter referred to as "CSO Basins: Getting
the..."). That report presents an excellent summary of the
insights and lessons learned from the design, construction, and
operation of the Rouge Project Phase I CSO facilities. The reader
is urged to review that full report for the detailed information.
Some of the information contained in that report is summarized below.
In addition, there is a wealth of additional and more detailed information
on the performance of the CSO treatment facilities on the Rouge
Project web site at the aforementioned "Technical
Papers and Professional Presentations."
While developing the summation of the data from the CSO basin evaluations,
four major evaluation questions emerged relative to the Rouge Project
CSO control program. Those questions were:
- How can compliance with NPDES Permits and Water Quality Standards
be measured?
- What treatment and hydraulic processes are most effective?
- What is needed for operational effectiveness?
- What is the proper size for CSO basins to comply with regulatory
requirements?
The answers to these questions are provided in the above referenced
report (CSO
Basins: Getting the...) What follows is a summary of that
report including the answers, the insights and lessons learned.
Evaluation Question 1: How Can Compliance With NPDES permits and
Water Quality Standards Be Measured?
Methodology for Evaluating CSO Basins
Following the implementation of the Rouge CSO control program,
the permittees and MDEQ realized that additional guidance was necessary
to define terminology such as "elimination of raw sewage".
As was discussed earlier, the methodology for evaluating the success
of the basins in meeting permit requirements was developed by the
MDEQ as part of its work with the Rouge Project. MDEQ developed
criteria for evaluating the success of the basins in meeting permit
requirements through close consultation with the owners of the facilities
and representatives of the Rouge Project. Two work groups were established,
one to evaluate individual basin performance and one to evaluate
the in-stream impacts for dissolved oxygen, physical characteristics,
total residual chlorine, and biological impacts. For each of these
evaluations, the work groups established a set of measurements and
analytical methods to perform the evaluation. This collaboration
resulted in a document entitled: "Criteria
for Success in CSO Treatment".
The goals and processes for evaluation of these goals established
as part of MDEQ's document are summarized in Table 3. Further description
of the importance of the collaborative, consensus building process
for the entire Rouge River restoration effort that included all
stake holder interests and focused on well-defined technical issues
are described in a paper titled: "Can a Watershed Be Managed?
Leading the Efforts of Public Agencies and Local Communities in
the Rouge River Watershed".
Table 3
Methodology for Evaluating Rouge Phase I CSO Retention Treatment
Basins
|
Goal
|
General Process to Evaluate Goal |
|
    1. Ability to compare data from all basins
|
Estimate actual detention times at design storms for each
facility to be able to compare basins on a common basis.
|
- Protect public health and eliminate raw sewage (Goal for
Phase I and Phase II Controls)
|
- Evaluate protection of public health based on disinfection
of effluent and determining if the effluent fecal coliform
limit of 400 cts/100 ml is met while minimizing total residual
chlorine (TRC).
- Evaluate elimination of raw sewage based on the ability
of the basins to remove sanitary trash and identifiable
sanitary solids. This evaluation to include:
- visual observations
- determining removal efficiency of materials greater
than 4-millimeters
- determining if any readily identifiable sanitary trash
is found in a 4-millimeter mesh effluent net or basket.
|
- Achieve state water quality standards in the receiving
stream at times of discharge (Goal for Phase III Controls)
|
Success of this goal are measured by the following criteria:
- The dissolved oxygen (DO) standard - measure DO to show
that the basin does not contribute to DO of less than 5
mg/L.
- The physical characteristics standard - measure TSS, turbidity,
oil and grease, and deposition areas to show the basin does
not contribute to violation of the physical characteristics
standard.
- The total residual chlorine (TRC) standard -measure TRC
to establish whether TRC plume will have toxic effects and
prevent fish passage.
- The health of the biological community (as a surrogate
for toxic materials and other pollutants) - measure the
health of the biological community using GLEAS* 51 procedures.
*Great Lakes and Environmental Assessment Section (GLEAS) Procedure
51 |
|
Utilizing the approximately two years of sampling
data at each basin, a detailed evaluation of nine
basins was undertaken to examine the performance
of the facilities relative to the three goals summarized
in Table 2. The River Rouge CSO basin did not become
operational until 2002. It is currently being evaluated
to determine its performance.
Goal 1: Ability to Compare Data for All Basins
The first goal or criteria for success was the
ability to compare data from all Phase I CSO basins.
The design approaches and assumptions used in the
design of the basins varied widely among the basin
designers. In order to draw conclusions about the
performance of the demonstration CSO basins, the actual basin
detention time at each facility given the same
storm event and conditions needed to be determined.
Knowing the actual detention time
versus a design detention time
provides a means of comparing the relative sizes
of these facilities and of comparing their size
to the demonstration and presumptive sizing criteria.
Then an evaluation can be made as to the effectiveness
of the residence time on settling and disinfection.
The CSO basin evaluation has resulted in the
following findings:
- The amount of runoff that is generated by a
storm event is greatly influenced by antecedent
moisture conditions. Antecedent conditions relate
to the amount of rainfall that occurred in the
days prior to the event being evaluated.
- The amount of runoff that is generated by a
rainfall event is greatly influenced by seasonal
variation in the infiltration capacity of the soil
and interception by foliage. A greater response
is seen during winter and early spring conditions
when infiltration capacity is lower or non-existent
due to frozen ground conditions and due to lower
interception by foliage (tree cover).
- The amount of runoff that is generated by a
rainfall event is greatly influenced by seasonal
variation in the peak hour intensity of the rainfall
events, which was also found to vary seasonally,
with higher peak intensities occurring during May
through October.
Thus, a design event cannot be adequately defined
without specifying these items.
These results illustrate the value of having
site-specific monitoring data to develop the parameters
used for sizing the basins. Critical in this sizing
analysis are a consideration of the seasonal variation
in rainfall intensities and the impact of antecedent
moisture conditions. Having sufficient data to
estimate flows that would be generated by a design
event is difficult, but it is vital to ensure that
the facility will be sized properly.
Because the actual detention times have been
determined to be greater than the original design
intended for three of the four basins analyzed,
it is important to look at the actual detention
time versus the design detention time in making
an assessment of how effective a CSO basin is in
meeting the regulatory requirements. The additional
detention time provided by these basins could be
providing additional treatment effectiveness. This
benefit needs to be considered in answering the
question of "What is the proper size for a basin
to meet regulatory requirements?"
Goal 2: Protect Public Health and Eliminate
Raw Sewage
The objective of Goal 2 is two-fold: a) the protection
of public health and b) elimination of raw sewage.
Success in achieving Goal 2 is demonstrated using
measurements and observations of CSO basin effluent.
Protect Public Health
The evaluation of the first part of Goal 2, protection
of public health, is based on disinfection of effluent
and determining if the Michigan fecal coliform
limit of 400 cts/100 ml is met by the effluent
while minimizing total residual chlorine (TRC).
A higher chlorine dose results in a greater treatment
of the fecal coliform, but it also tends to result
in a higher TRC. At the start of the project, the
goal for CSO basin effluent TRC was 1 mg/L or lower.
Individual effluent samples collected during a
range of events were tested for fecal coliform
concentrations and discrete measurements of TRC
were also made. For each facility and storm, an
event geometric mean for effluent fecal coliform
and an event mean TRC value were calculated. Success
is judged to be achieved if the event geometric
mean fecal coliform across the range of monitored
storm events is in compliance with the limit.
The results of the basin evaluations indicate
the facilities can consistently meet the fecal
coliform limit when operated to maintain effluent
TRC concentrations of 1 mg/L or greater. For discharge
events with effluent TRC concentrations less than
1 mg/L, the fecal coliform limit was usually not
met. As a result of the evaluation and a consensus
by one of the Rouge Project work groups, the target
range for effluent TRC was revised from 1.0 to
1.5 mg/L.
Eliminate Raw Sewage
The second part of Goal 2, determining if the
basin eliminates raw sewage, is based on the ability
to remove sanitary trash and identifiable sanitary
solids. The basis for this criterion is that the
discharge can only be considered treated and no
longer raw if it does not have the visual appearance
of raw sewage (in addition to being disinfected).
Removal of sanitary materials includes three process
treatment components: screening, skimming and settling
of the flow. Screens installed at each facility
contribute to the removal of larger debris from
the flow. Baffle walls installed in the vicinity
of influent, intermediate or discharge weirs help
to facilitate the removal of floating materials.
These materials are captured in the basin for removal
during dewatering or flushing. Sedimentation allows
for the removal of heavier objects and solids.
The ability of the facilities to achieve removal
of these objects is typically related to the surface
overflow rate and the weir loading rate.
Elimination of raw sewage was evaluated by visual
observations and a netting study. Visual observations
were performed during daylight hours at the four
CSO basins where it was feasible, and were taken
as representative of the other basins. Mesh nets
with small rectangular openings of 6 mm were placed
over a portion of the basin outfall grating at
4 basins to determine if any sanitary trash were
being discharged from the basin to the river. No
evidence of sanitary trash was seen in the effluent
of those basins observed, except for a small amount
on one occasion. This event was not viewed as a
concern as it was caused by abnormal basin operation
following a power failure.
It is very important to note that based on
the evaluations performed on the effluent discharge
from the basins, MDEQ has concluded that all nine
of the Rouge Phase I CSO basins evaluated are
currently meeting the Goal 2 criteria of the elimination
of raw sewage and the protection of public health. The
tenth facility is still being evaluated.
Goal 3: Achieve State Water Quality Standards
The objective of Goal 3 is to achieve state water
quality standards in the receiving stream at times
of discharge. Success in achieving Goal 2 (protect
public health and eliminate raw sewage) is demonstrated
using measurements of basin effluent, whereas the
success in achieving Goal 3 is demonstrated using
measurements in the receiving stream at times of
discharge. The four criteria of success for Goal
3 as outlined in Table 3 are 1) the dissolved oxygen
(DO) standard, 2) the physical characteristics
standard, 3) the total residual chlorine (TRC)
standard, and 4) the health of the biological community
(as a surrogate for toxic materials and other pollutants).
Dissolved Oxygen Standard
The state's DO standard for the Rouge River is
a minimum of 5 mg/L at all times. To achieve Goal
3 for the DO standard required measuring DO in
the river both upstream and downstream to show
that the basin does not cause the DO to go below
the standard of 5 mg/l. This criterion was evaluated
by continuous water quality monitoring stations
and predictive modeling to determine the magnitude
and location of transitory dissolved oxygen sags
caused by effluent from the facilities.
All available monitoring data and modeling results
have led to the following findings:
- The DO standard is being achieved downstream
of all three Oakland County CSO basins at times
of discharge, except for DO sags that were not
caused by the basin effluent.
- At times of basin discharge, the DO standard
is being achieved from the Redford basin down to
a location where other uncontrolled CSOs impact
the river. DO did sometimes drop below the standard
during wet weather events, but since this pattern
was nearly identical upstream and downstream of
the Redford basin, the cause of the violation was
not attributed to the basin.
Physical Characteristics
The state's physical characteristics standard
prohibits unnatural physical properties (turbidity,
color, oil films, floating solids, foams, settable
solids, suspended solids, deposits) in quantities
which are, or may become injurious to any designated
use of the receiving stream.
The physical characteristics criterion was evaluated
by comparing effluent and instream total suspended
solids, and by periodic visual observations of
the effluent plumes, primarily to check for the
presence of oil films or high turbidity. Also,
effluent nets on the CSO discharges were used to
determine if any sanitary trash or identifiable
sanitary solids were present in the effluent. The
documented data for the physical properties considered
indicate there are no unnatural physical properties
in quantities that are considered injurious to
any designated use at times of basin discharge.
Total Residual Chlorine
As required by the state water quality standards,
instream TRC concentrations must not exceed the
final acute value of 0.038 mg/L, unless a mixing
zone demonstration is performed and accepted by
the state. This standard is difficult to meet given
that effluent TRC must be at least 1 mg/L for adequate
reduction of fecal coliform bacteria. The TRC standard
was evaluated by measuring instream TRC concentrations
downstream of CSO basin discharges. Due to difficulties
in safely accessing the river during high flow
conditions, these measurements were limited to
one facility where a boat could be used to perform
instream sampling. While instream TRC concentrations
in excess of 0.038 mg/L were measured near shore
at several downstream transects, the concentrations
were below detection for two-thirds of the river
cross-section. While the results show there is
a zone for fish passage, a formal mixing zone demonstration
was not performed for the facility.
In summary, the evaluation performed to date
has shown that instream TRC measurements have exceeded
the state standard, but there has been no conclusion
regarding the specific environmental impact caused
by chlorine residuals in the Rouge River. As the
next step in the evaluation process, the NPDES
permit for the three Oakland County CSO basins
requires that a TRC Mixing Zone/Plume Definition
Study be performed for each basin. The purpose
of the study is to determine the water quality
impacts in the Rouge River from TRC in the treated
basin effluent. The permit required a work plan
for the study to be submitted in September 2003
with the study report to be submitted by March
2006. If the study indicates that effluent limitations
or additional controls for the discharge of TRC
are needed to meet water quality standards at times
of discharge, the MDEQ may propose to modify the
NPDES permits for these three basins to include
appropriate effluent limitations and/or controls
for the discharge of TRC.
Biological Assessment
Finally, the health of the biological community
was assessed in the vicinity of several Rouge Phase
I CSO basin discharges as a surrogate for assessing
the presence of toxic materials and other pollutants
in the basin effluent. Macroinvertebrate samples
were collected upstream and downstream of the CSO
basins in Redford and Oakland County (four basins
total) to investigate the compliance of these basins
with Goal 3. Collection of organisms and calculation
of community scores followed the Great Lakes and
Environmental Assessment Section (GLEAS) Procedure
51 (MDNR, 1991). As a result of this assessment,
it was agreed by MDEQ that the water quality standards
for toxic substances are presumed to be achieved
upstream and downstream of the Oakland County and
Redford CSO basins, even at times of discharge,
as there is no measurable effect of these discharges
on the health of the biological community.
Summary
It is very important to note that evaluations
relative to Goal 3, achieving state water quality
standards, have been completed at three of the
Rouge Phase I CSO basins and MDEQ has certified
that these basins are meeting water quality standards
at times of discharge, except for meeting the
yet-to-be-evaluated total residual chlorine standard.
This certification is expected for at least another
three basins in the year 2004. Additional
details of the in-stream evaluation process can
be found in the paper titled "Evaluation
of In-Stream Impacts of CSO Control Facilities" Trend
analysis results clearly demonstrate that DO concentrations
are improving in the Rouge River Watershed during
both wet and dry weather conditions. Eight of
nine locations show a statistically significant
improving trend for the mean DO with the annual
average improvement ranging up to 0.53 mg/L per
year. The ninth location is still being evaluated
and is influenced by many uncontrolled CSO outfalls.
Lessons Learned on Evaluation Question 1
Lessons learned relative to evaluating compliance
of the Rouge Phase I CSO basins with regulatory
requirements include the following:
- Regulatory requirements can be ambiguous; thus,
developing a well defined, technical evaluation
process was critical to determine compliance with
regulatory requirements. Use of collaborative work
groups that involved all the stakeholders provided
important consensus on defining criteria for success.
- The process for evaluating the impacts of the
basins has led to constructive decisions. Working
with a large group trying to achieve consensus
has taken more time, but was well worth the effort.
MDEQ agreed that implementation of further controls
is dependent on this evaluation.
- A design event cannot be adequately defined
without specifying antecedent conditions, season,
and rainfall intensity. These factors all impact
the amount of wet weather response that will be
generated for the same size storm event. Ideally,
continuous simulations that account for these factors
by using rainfall records over a number of years
should be used to predict runoff rates and volumes.
These simulation results would better predict the
performance of the basins in terms of frequency
and volumes of CSO captured or overflowed.
- The Rouge Phase I CSO basins provide retention
and treatment and the frequency and magnitude of
discharges has been considerably reduced. Therefore,
the basins only discharge treated effluent in large
events when assimilative capacity of the river
is the greatest.
- Other sources of water pollution are significant,
but the evaluation of CSO impacts can be reasonably
isolated from other non-point source pollution
impacts to draw conclusions on the effectiveness
of the CSO basins in achieving the water quality
standards.
- A two-year time frame for monitoring and/or
10 overflow events at each facility is generally
sufficient to characterize effluent quality, demonstrate
ability to meet effluent permit limits, and demonstrate
ability to meet water quality standards at times
of discharge. In some cases, an additional 3 to
6 months of study is being performed to further
examine some issues specific to certain basins.
- Treated effluent from the CSO control facilities
studied so far seems to be relatively good quality.
Permit effluent limits for fecal coliform can be
met consistently when effluent TRC is greater than
1 mg/L. Water quality standards are being met at
some facilities, but detailed evaluations are ongoing
for the other basins, particularly for DO.
8. Instream
TRC from basin effluent exceeds
state standards at times, but
further evaluation is needed
to determine if there is any
adverse environmental impact.
Overall, the evaluation of the Phase 1 CSO control
facilities is providing valuable technical information
for future phases of CSO control in the Rouge watershed
and for communities embarking on CSO control in
other watersheds. The development of an evaluation
process provided an innovative forum for stakeholders
to collaboratively establish objectives for CSO
control within the goals of urban watershed restoration.
Since wet weather control is expensive, having
a well defined, technical evaluation process to
determine compliance with regulatory requirements
is important.
Evaluation Question 2: What Treatment and Hydraulic
Processes Are Most Effective?
Treatment and Hydraulic Processes
Used
A variety of design features were employed to
explore what treatment and hydraulic processes
are most effective in reducing CSO loads to the
river. The Rouge facilities all included influent
or effluent screens, skimming baffles, storage
and settling compartments within the basins that
can capture small events or work in a flow-through
mode for large events, and disinfection using sodium
hypochlorite. The facilities also included a variety
of innovative technologies: swirl concentrator,
first flush compartments, compartments in parallel,
compartments in series, decanting outlets and shunt
channels
A summary of the basin configuration and size
for the nine Rouge Phase I CSO basins in operation
is provided in Table 4. Six of the facilities have
the ability to capture the first flush; that is,
to route flows to a second flow-through tank after
the first tank/compartment is full. This prevents
the discharge of any loads that may be captured
with the first flush, which has been found to have
higher concentrations of pollutants. One facility
has a swirl concentrator, and three facilities
have a shunt channel to avoid potential for resuspending
solids after the facility is full. For screening,
most of the facilities used a bar spacing of 0.75
inches. Two basins used screen bar spacing of 0.5
inches and one used 1.5 inches.
Table 4
Rouge Phase I CSO Basin Configuration and Size
Basin |
Configuration |
Dimensions |
Compartment Volumes (MG) |
Inkster |
1 first flush compartment followed by 2 detention compartments operating in parallel |
186 ft x 60 ft x 11.75 ft each detention compartment |
First flush compartment = 1.1 MG
2 detention compartments, each = 1 MG
Total = 3.1 MG
|
Redford |
2 parallel compartments preceded by one swirl concentrator |
180 ft x 66 ft x 11.2 ft each compartment |
Each compartment = 0.95 MG
Total = 1.9 MG
|
Dearborn Heights |
3 detention compartment in parallel with the capability of using the first compartment for a first flush capture |
175 ft x 60 ft x 11.6 ft each compartment |
Each compartment = 0.9 MG
Total = 2.7 MG
|
Acacia Park |
2 compartments in series |
160 ft x 80 ft x 20 ft each compartment |
Each compartment = 2.0 MG
Total = 4.0 MG
|
Birmingham |
2 compartments in series with 11ft tunnel |
140 ft x 120 ft x 20 ft each compartment |
Each compartment = 2.75 MG
Total = 5.5 MG
|
Bloomfield Village |
3 compartments filling in series through weirs at different elevations |
157.5 ft x 128.5 ft x 20 ft each compartment |
Each compartment = 3.3 MG
Total = 10 MG
|
Seven Mile |
2 compartment operating in parallel |
200 ft x 91.5 ft x 8 ft each compartment |
Each compartment = 1.1 MG
Total = 2.2 MG
|
Puritan Fenkell |
2 compartment operating in parallel |
236 ft x 99.5 ft x 8 ft each compartment |
Each compartment = 1.4 MG
Total = 2.8 MG
|
Hubbell-Southfield |
2 compartment in series with the capability of running the first compartment as a first flush capture compartment |
900 ft x 240 ft x 16.5 ft overall each compartment |
First compartment = 10 MG
Second compartment = 12 MG
Total = 22 MG
|
River Rouge |
2 compartments filling in series |
First compartment = 135 ft diameter x 38 ft high.
Second compartment 135 ft diameter x 14 ft high |
First compartment = 1.4 MG
Second compartment = 3.8 MG
Total = 5.2 MG
|
For achieving disinfection, the basins were designed
around dosing concentrations of 10 to 11.6 mg/L
and assuming the sodium hypochlorite is stored
at a 5 to 6 percent solution. Design dosing rates
ranged from 1,400 to 12,600 gal/hr.
Results of Evaluation Question 2
The primary treatment process that is most effective
is simply the size of the overall basin that translates
into volume captured by the basin. The larger the
basin, the lower the volume and frequency of overflow
will be.
The evaluation of the different design features
and capacities of the Rouge River CSO basins provide
a basis for comparing the respective operating
performances of the different components and different
basis of sizing. As more operating experience is
gained, the benefits of first flush tanks, tanks
in series versus tanks in parallel, and shunt channels
will be able to be better quantified.
Decanting of stored and treated CSOs is a potential
procedure that is being considered. Decanting refers
to the practice of screening, chlorinating, and
settling CSO in the basin, then releasing a portion
of the treated effluent to the receiving water.
Tests are being performed and submitted to the
Michigan Department of Environmental Quality for
review. In one test in January 1999, the treated
effluent had Carbonaceous Biochemical Oxygen Demand
(CBOD) and TSS less than 20 mg/L, and the bacteria
and TRC standards were also met. This practice
has the advantage of enhancing flows in the river
and avoiding the cost of treating the flow again
at the wastewater treatment plant.
Based on the two years of experience, it is clear
that more design attention should be paid to how
the basins can be operated in low flow conditions.
Much of the design effort for any CSO control facility
focuses on performance under peak flow conditions.
However, there are usually dozens of events each
year that are smaller events with low flows. In
fact, low flows accounted for over 80 percent of
the events in the Rouge watershed. Supervisory
control and data acquisition (SCADA) and weather
radar information is critical to monitoring flows
and storms to know how to initially respond to
small events and low flow rates. Also special operating
procedures are required to accurately monitor low
flows. The multi-path ultrasonic flow meters that
are used at the Rouge Phase I CSO basins are good
for high flows, but they have not proven to be
accurate under low flow collection conditions,
especially when the water level within the collection
system and CSO basin rises. At low flows, it is
particularly difficult to accurately determine
the proper rate of chlorine addition. Continuing
operating experience is required to establish standard
operating procedures for low flow conditions.
Better estimates of the effectiveness of the
mixing of the sodium hypochlorite with the CSO
influent is needed to better assess the impact
of mixing to disinfection effectiveness. A standard
methodology for evaluation of the mixing process
would be helpful for evaluation of this aspect
of the basin processes.
At this time, additional investigation is underway
to "stress test" the swirl concentrator in the
Redford CSO facility and to determine the performance
of this unit separate from the detention basins
that are also part of the facility. These tests
will improve operating protocols for determining
how the swirl concentrator should be used in conjunction
with the basins.
Lessons Learned on Evaluation Question 2
The Rouge Project has evaluated CSO discharge
data in the Rouge watershed and influent and effluent
quality data from existing CSO basins in Michigan.
Analysis was performed using results from 390 CSO
storm water runoff events in the Rouge River watershed
and from 44 events at CSO basins outside of the
watershed. The following lessons learned were developed
from this analysis:
- Samples collected at CSO discharges confirm
that pollutant concentrations decrease over the
course of the discharge event. This phenomenon
has been identified for CSO discharges for years
and is referred to as a first flush phenomenon,
with the first flush generally defined as the first
30 minutes of a storm water runoff event.
- Samples collected of the influent to the facilities
indicate that smaller events have greater pollutant
concentrations than larger events. In addition,
the smaller events, which are captured by the facilities
for subsequent discharge back to the collection
system after the storm event, account for over
80 percent of the events.
- Because the facilities can contain the smaller
events with the higher pollutant concentrations,
the annual pollutant load captured is much greater
than the annual volume captured. The use of first
flush compartments to capture the first portion
of larger events also contributed to this result.
- The magnitude of CSO pollutant load reduction
is related more to capture of concentrated portions
of the flow than removal by settling. Thus, use
of first flush compartments and flow bypass (shunting)
were included in the design of some of the facilities.
No significant removal of BOD, ammonia or phosphorus
(other than related to volumetric capture) was
apparent in the facilities.
- CSO pollutant quality during larger wet weather
events (those that would activate a treatment facility)
was generally quite dilute for the following parameters:
BOD (series), ammonia and phosphorus.
- Effluent quality was generally low in BOD ( < 30
mg/L).
- Significant reductions in TSS were noted for
flow through processes even with loading rates
as high as 7,900 gpd/sf.
- Removal of visible sanitary trash was accomplished
through a combination of settling/baffling system
and screens. It was unresolved whether fine screens
were necessary to achieve this performance objective
in facilities where settling and skimming were
provided. Moreover, the following was not determined:
- Maximum screen size that
would work when settling
and skimming are provided.
- Screen size necessary
when degree of settling
and skimming is reduced
due to either a condition
of a smaller basin facility
or use of a flow through
facility, such as a tunnel.
A tunnel or a smaller basin
that operates in a flow-through
mode would not offer the
settling velocity characteristics
provided by the basin facilities
evaluated for this document.
- Effective disinfection of discharges was accomplished
with sodium hypochlorite. Minimum detention times
at peak overflow conditions rarely fell below 30
minutes. The relationship between detention time
and reduction in bacteria colonies could not be
determined; however, for the events monitored,
the results suggested that the detention time provided
was not the controlling factor.
- First flush capture compartments assisted in
the effective disinfection of discharges with less
variability in results.
- The wide range of flow rates with various levels
of solids though the facility must be carefully
considered in the design of the hydraulics and
mechanics of moving flows. For instance, an underflow
pump was installed without consideration of need
to handle solids and grits, causing problems with
the operation of this part of the flow stream through
the facility.
Evaluation Question 3: What is Needed for Operational
Effectiveness?
In addition to the effectiveness of the design
of the various treatment and hydraulic processes
employed at the Rouge Phase I CSO basins, the effectiveness
of the operation of these processes is also critical
to the successful performance of the basins. The
process features of each facility include retention
(storage), screening, and disinfection of the discharge
with sodium hypochlorite. In addition, equipment
is provided to clean the facility following an
event, monitor flow rate and volume, collect samples,
and return flow to the interceptor system (dewatering).
The facilities have computer control systems with
varying degrees of sophistication.
Operating data collected since June 1997 provides
important information on design features and on
various aspects of operating CSO facilities. The
Rouge CSO control facilities have been activated
on average once or twice per month. The Hubbell-Southfield
facility is activated most frequently, because
the overflow point that it serves has the largest
drainage area and smallest relative capacity for
transmission of wet weather flows downstream for
treatment. Elsewhere, the storage capacity and
dewatering capacities have been exceeded on average
only 2 to 4 times per year, depending on the facility.
When storage capacity is exceeded the basins provide
settling, screening, and disinfection of the discharge.
The success of a facility's operation is dependent
on the ability of the facilities to reliably meet
permit and other regulatory performance measures.
Of particular interest is the relationship between
the water quality benefits of certain design features
and the practices in operating these features.
The following discusses the operation and performance
of disinfection, screening, dewatering, and flushing.
Training of staff, use of mobile staffing, control
systems, and monitoring are additional aspects
of operating a facility effectively that are also
discussed.
Staffing
The 10 Rouge Phase I CSO retention treatment
basins include three operated by the City of Detroit
Water and Sewerage Department (DWSD), three operated
by the Oakland County Drain Commissioner, and four
operated by the Wayne County Department of Environment.
The local communities assist Wayne County at two
of these basins.
The Wayne County and the DWSD basins have no
full-time staff except for at the Redford basin,
which has one full-time staff person. The Oakland
County basins have one full time staff person per
basin. All basins rely on mobile crews and have
SCADA technology for operational control. Existing
staff persons with pump station and wastewater
sampling experience were selected to form the core
group of CSO basin operating, sampling and maintenance
group.
Each operating agency has a somewhat different
staffing plan. The basins operated by Wayne County
use a 3-person team per basin, and each team is
mobile. The basins operated by the Oakland County
Drain Commissioner have a mobile supervisor plus
one person stationed full-time on day shift at
each basin. The DWSD facilities use a 3-person
team per basin, and each team is mobile. The basins
are within 4 to 13 miles of home base for all three
operating agencies.
In October 2000, the operators participated in
an "Operator
Forum" to provide feedback on the equipment
and operational characteristics of their facilities..
A number of their comments are included in the
discussions on the various operations provided
in the following sections. The comments relate
to experience at nine of the basins, as the River
Rouge basin was not operational at the time of
the forum.
Operations Evaluated:
Monitoring Program
Detailed plans for performance monitoring were
developed in collaboration between the owners of
the facilities, the MDEQ, and representatives of
the Rouge Project. The purpose of the monitoring
plan was to assess the relative effectiveness of
the different basin sizes, storage configurations,
treatment technologies and operational practices
used in the facilities. The evaluation program
was complex, and it was a significant factor in
the operation and maintenance requirements for
the basins in the first two years of operation.
Details of the full monitoring program can be found
in "CSO
Basins: Getting..." Comments received
from the operators on flow monitoring and sampling
are detailed in the above report.
Disinfection
All facilities are designed to meet NPDES effluent
limits for fecal coliform of 400 cts / 100 ml and
an effluent goal for total residual chlorine (TRC)
of 1 mg/L. Operational control is based on monitoring
the influent flow and effluent TRC.
Disinfection is achieved using liquid sodium
hypochlorite. Details of the disinfection process
used can be found in "CSO
Basins: Getting..."
There are several operational problems that have
arisen with the chlorination systems. For example,
first, there has been more rapid degradation of
the strength of the stored sodium hypochlorite
strength between storm events than anticipated.
Second, there is the tendency for the flow meters
to under-record flow rates at low flows as the
water level is rising. As a result, this causes
too little hypochlorite to be applied. Third, there
was a problem getting accurate measurements of
effluent TRC. The report "CSO
Basins: Getting..." contains comments
received from operators on the disinfection system
and its operation.
Screening
All facilities were designed to provide screening
of the CSO basin flows. Successful removal of sanitary
material is defined by MDEQ's criteria as the removal
of sanitary trash with a size of 4 mm or greater.
Subsequent studies of the effluent of the facilities
have shown that the sanitary trash removal goals
are met for the facilities evaluated.
The size of screenings collected ranged from
sanitary trash to tires. The Wayne County and Detroit
facilities rely on influent mechanically cleaned
bar screens with spacing that varies from 0.5-inch
to 1.5-inch. The Oakland County facilities use
effluent static upflow screens with 0.75-inch spacing.
Following the conclusion of a wet weather event,
the material that has accumulated on the screen
is sent to the interceptor with the dewatered flow.
The dewatering wet wells for the Oakland County
facilities also have bar screens. Operators try
to force the screenings through to the interceptor.
The retained screenings are scraped and disposed
to a landfill.
In general, the operators have been relatively
satisfied with the screening equipment and operation
of the screens. The report "CSO
Basins: Getting..." contains comments
received from operators on the screening system
and its operation.
Dewatering
The basins are dewatered after an event, when
capacity is available in the receiving interceptor.
The Wayne County facilities dewater by gravity,
with the rate controlled by a control valve. A
meter provides information in the downstream interceptor.
The Oakland County basins are dewatered by pumping.
A SCADA system is used to monitor levels in the
receiving interceptors as well as total discharge
rate at their point of connection to the DWSD system
to ensure that peak contract capacity is not exceeded.
The Detroit basins are pumped, though the top 9-feet
of the Hubbell-Southfield facility is dewatered
by gravity. Level indicators are provided in the
downstream interceptor. Significant maintenance
issues include the need to visit sites regularly,
reliability of the SCADA system, and maintaining
the dewatering pumps and the sump pumps.
The time required for basin dewatering ranges
from 5 to 45 hours. The time required depends on
the volume stored, the interceptor capacity available
and in some cases also depends on the dewatering
pumping capacity.
Flushing
Eight of the Rouge Phase I CSO basins use tipping
buckets to remove settled debris after an event.
The ninth and largest facility, Hubbell Southfield
Basin, uses flushing nozzles. In some locations,
there are auxiliary hoses to clean debris from
wet wells and channels.
In general the tipping buckets
are proving to be adequate. In some cases, where
there is a long flushing length to clean, the process
needs to be repeated several times and manual cleaning
of some corners and walls is required.
The flushing nozzle system installed in the one
facility has been a disappointment. The pressure
maintained in the system has not been adequate
to scour deposited solids from the floor. These
nozzles are located near the ceiling of the facility.
Older CSO facilities operated by Wayne County and
Oakland County also use flushing nozzle systems.
Both of these agencies are satisfied with the performance
of these systems. The Wayne County facility has
the nozzles mounted near the floor, and the Oakland
County system has jets that are intended to flush
debris to a center trough, where the bulk of the
material is removed manually.
The report "CSO
Basins: Getting..." contains comments
received from operators on the flushing process
and its operation.
Control Systems
The CSO facilities have varying degrees of control
systems. The control systems help to determine
the status of various components of the facility
and the adjacent collection system, as well as
various degrees of remote monitoring and operation.
The ability to remotely monitor
the facilities is critical as this helps to determine
when staff needs to be mobilized. At this time,
remote operation of the facilities during an event
is not considered feasible, regardless of the sophistication
of the control system. Experience to date demonstrates
that staff must be present during events for proper
operation.
The report "CSO
Basins: Getting..." contains comments
received from operators on the control system and
its operation.
Lessons Learned on Evaluation Question 3
Operational lessons learned from the Rouge Phase
I CSO basins include the following:
- 1. Protocols for items such as chemical feed,
flow monitoring and sampling are often different
for smaller wet weather events. As the vast majority
of events will be small, the facility design should
also recognize the operational differences for
small storms.
- Sodium hypochlorite disinfection systems need
to address proper materials for long life, system
flushing, testing of stored solution, and flow
pacing of chemical addition.
- Complex hydraulics, intermittent events and
highly variable flow rates made the use of high
tech flow metering equipment problematic. The best
flow measurement results were achieved by metering
with Parshall flumes and by calculating flows from
pump capacity and run times.
- Process flow control needs to be able to respond
to highly variable flow rates. For example, a static
weir for flow splitting is preferable to meter/
valve arrangements. Additionally, gate-closing
action may not be quick enough for wet weather
flow variations.
- Regardless of level of automation, facilities
generally require staff presence during wet weather
events.
- Start-up and testing of any CSO basin will likely
take at least two years to fine tune, depending
on the frequency of overflow events. Because most
overflows from the combined sewer system were contained
in the basins, there were very few events (e.g.,
2 to 4) each year through which operators were
able to develop experience with the flow-through
operation of the facility.
Evaluation Question 4: What is the Proper Size
for CSO Basins To Comply With Regulatory Requirements?
The Rouge Project was initiated in part to answer
this very question. Since wet weather control is
|